File imagery: Psyche, 13 October 2023. Falcon Heavy lifting off from Launch Complex 39A.
Credit: NASA/Aubrey Gemignani · Public domain (NASA) · SourceGriffin Mission One
Falcon Heavy, SpaceX
No earlier than
Wed 6 Jan 2027
Day known, time to come
We last checked
The mission
A Falcon Heavy will launch Griffin Mission One to lunar orbit from Kennedy Space Center, Florida.
Demonstration flight of the Astrobotic Griffin lander and its engines, initially contracted for the NASA VIPER (Volatiles Investigating Polar Exploration Rover) mission. The vacated payload spot will now host the FLIP (FLEX Lunar Innovation Platform) lunar rover from Astrolab.
- Mission type
- Lunar Exploration
Schedule changes
First dated 9 November 2026.
First dated: Wed 6 Jan 2027
NET January 6.
Launch Library 2 update. Read the source update
Rocket
Falcon Heavy
- Reusable
- 14 launches so far
- Family
- Falcon
- Manufacturer
- SpaceX
Launch site
Launch Complex 39A
Kennedy Space Center, FL, USA
28.61° N, 80.60° W
Open in mapsHow we know
The data on this page comes from Launch Library 2.
We last checked . We check Launch Library 2 about every ten minutes.
Launch Library 2 last changed this launch .
“Day known, time to come” means the launch day is set but the time is not. The countdown starts once it is. How to read launch times
Related launches follow the listed dates, which can change.
Every change and update (19)
We started following this launch on .
- We recorded
Window close moved from Sun 31 Jan 2027, 00:00 UTC to Wed 6 Jan 2027, 00:00 UTC
- We recorded
Window opening moved from Sun 31 Jan 2027, 00:00 UTC to Wed 6 Jan 2027, 00:00 UTC
- We recorded
Date became more certain: from Month to Day
- We recorded
NET moved from NET January 2027 to NET Wed 6 Jan 2027
- Launch Library 2 update
NET January 6.
Read the source update - We recorded
Window close moved from Thu 31 Dec 2026, 00:00 UTC to Sun 31 Jan 2027, 00:00 UTC
- We recorded
Window opening moved from Thu 31 Dec 2026, 00:00 UTC to Sun 31 Jan 2027, 00:00 UTC
- We recorded
NET moved from NET December 2026 to NET January 2027
- Launch Library 2 update
Delayed to NET January.
Read the source update - Launch Library 2 update
NET December.
Read the source update - Launch Library 2 update
NET November.
Read the source update - Launch Library 2 update
NET H2 2026.
Read the source update - Launch Library 2 update
NET July 2026
Read the source update - Launch Library 2 update
NET 2026.
Read the source update - Launch Library 2 update
NET December.
Read the source update - Launch Library 2 update
NET November 2025.
Read the source update - Launch Library 2 update
VIPER cancelled, but launch of the lander still scheduled for fall 2025
Read the source update - Launch Library 2 update
NET 2025.
Read the source update - Launch Library 2 update
Mission delayed due to NASA's request for additional lander tests
Read the source update